Capital Improvement Projects

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

What We Build Matters

Together as a community, we’ve invested in essential facilities, services and structures that support your daily life. That’s why the work of building things like roads, parks and water reservoirs for the community gets labeled “public works” – these projects benefit the public, all of us. 

Capital Improvement Plan 

The Capital Improvement Plan (CIP) is Tigard's 5-year plan for matching the cost of large-scale improvements—like fixing roads, water and sewer systems—to anticipated revenues, like taxes and bonds. Learn more about our projects below. 

Project Description

The Bonita Road and Sequoia Boulevard intersection, near I-5, is a busy intersection in Tigard. Washington County will install a traffic signal to improve safety and traffic flow.
Other improvements include:

  • Crosswalks
  • ADA-compliant curb ramps
  • Some storm drain updates

This project is managed by Washington County. The City of Tigard has been and will continue to be involved throughout the duration of the project. 

Project Updates

Project is in construction phase. Traffic on Bonita will be restricted during the hours of 9:00 a.m. to 3:30 p.m., except Fridays from 9:00 a.m. to 3:00 p.m. As the project progresses, updates will be available on the Washington County project page.

Why It's Needed

This is a high-priority safety project. The intersection has a high crash rate and other traffic issues.

Strategic Plan Tie-in

This project supports the goal of ensuring transportation investments and improvements provide equitable benefits and impacts to the entire population. It also helps ensure that development and growth support the city’s vision.

Timeline

 FY24- FY27

Design Start: June 2024
Construction: Summer 2026
Project Completion: Late Summer 2026

Funding Source

 Washington County selected this project for the Major Streets Transportation Improvement Program (MSTIP) and will provide most of the funding and project implementation. City of Tigard funding will come from the Transportation Development Tax.

Operation and Maintenance Costs

 This will require increased payments to Washington County to maintain an additional signal and also a slight cost increase for restriping.

Contact

Trent Brickey, Project Coordinator: 503-718-2686trentb@tigard-or.gov

Return to full list >>