Capital Improvement Projects

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

What We Build Matters

Together as a community, we’ve invested in essential facilities, services and structures that support your daily life. That’s why the work of building things like roads, parks and water reservoirs for the community gets labeled “public works” – these projects benefit the public, all of us. 

Capital Improvement Plan 

The Capital Improvement Plan (CIP) is Tigard's 5-year plan for matching the cost of large-scale improvements—like fixing roads, water and sewer systems—to anticipated revenues, like taxes and bonds. Learn more about our projects below. 

Project Description

The Red Rock Creek Stabilization and Enhancement project will provide stream enhancements and long-term stabilization to Red Rock Creek from just downstream of Southwest Dartmouth Street upstream to SW 72nd.  

Project Renderings (PDF)

Timeline

July 2025: Contractors will be preparing the site by removing required trees and debris from the work area. 

August-September 2025: Stream improvements will be taking place near Costco and Winco. There will also be culvert rehabilitation work on Dartmouth Street.

September- November 2025: Sanitary sewer realignment and box culvert construction will be taking place in the former Tigard cinema site. 

June-September 2026: Steam improvements will be taking place in the former Tigard cinema site. 

End of September 2026: Project completed. 

Why It's Needed

The portion of Red Rock Creek located in the Tigard Triangle area has experienced hydromodification from past development resulting in severe erosion and incision.  This erosion and incision, in some areas up to 25 feet deep, has resulted in a sanitary sewer line being exposed and has caused multiple line breaks requiring extensive repairs.  Eroded sediment has also settled in areas from just upstream of Southwest Dartmouth downstream to the confluence of Fanno Creek, resulting in the degradation of wetlands and localized flooding at Southwest Dartmouth.  Development in the Tigard Triangle and Hunziker area will add stormwater runoff and contribute to the degradation of the creek and its floodplain.

Strategic Plan Tie-In

This project relates to Objective 3.2, Action F of the Strategic Plan by protecting and restoring the ecological function of Red Rock Creek.

Funding Source

Sanitary Sewer, Stormwater, and Urban Renewal funds.

Operation and Maintenance Costs

Reduced maintenance due to stabilization.

Contact 

Andy Newbury, Principal Engineer: 503-718-2472andrewn@tigard-or.gov