|
Project Status
|
Project Update 9-1-2010
Through October, the contractor is excavating for the proposed pump station and valve vault. This phase of the project entails excavating, moving, and transferring material on and offsite. The contractor is operating heavy excavating equipment and loading and unloading dump trucks. As the excavation increases in depth, the contractor will install a temporary shoring system in order to keep the excavation pit from collapsing. Shoring is a general term used in construction to describe the process of supporting a structure in order to prevent collapse so construction can proceed. For this project, the process involves excavating five feet in depth, installing shoring nails, applying a steel mesh and covering with concrete.
|
Temporarily shoring for the proposed pump station.
|

Contractor is installing soil nails in the valve vault.
|
|
Project Update 8-1-2010
Over the past several months, the contractor has removed pavement and installed water lines
in 125th and in Bull Mountain Road, a temporary pump station has been installed at another
water facility, and the existing pump station on site has been decommissioned. Portland
General Electric and Comcast have underground their utilities along Bull Mountain Road.
The next phase of the project will be the excavation for the new pump station and valve vault.
Starting this week and continuing into September, you will experience excavation equipment,
dump trucks, concrete trucks and other excavation and shoring equipment.
|
Heavy excavation equipment excavating approximately 40 feet in depth in order to prepare for the pump station.
|

Contractor is preparing the foundation for a new architectural wall that will be located along the south and east sides of the water site. Fill material will be brought in to increase the height in order to match the elevation of Bull Mountain Road. Adjacent to the architectural wall the contractor will install a concrete side walk the length of the property line.
|
Building a foundation for the new generator. This generator will power the new pump station and/or the existing aquifer storage and recovery well during emergency power outages.
|
Project Update 6-5-2010
|
The City's contractor is currently installing a temporary water pump station. This pump station will provide drinking water to residences, schools and commercial buildings on Bull Mountain from a drinking water reservoir located on the west side of Bull Mountain while the new pump station at 125th and Bull Mountain Road is being constructed.
|

The City's contractor is installing on-site piping that will convey water from the new pump station to the drinking water supply system.
|
 Moving the job site trailers and installing construction fencing in preparation of the next phase of the project.
|
Project Update 5-17-2010
|
PGE crews are dropping power from overhead lines to
underground conduit from Hazeltree to 126th along Bull Mountain Road.
|

City's contractor is installing waterlines and electrical conduit in
125th.
|
 City's sub-contractor is installing electrical vaults along 154th and
PGE crews.
|