Elizabeth Price Park/Reservoir
|
550' Zone Reservoir No.2 and Supply Piping
This reservoir will be located on Bull Mountain and will serve the south and eastern
portions of the 550-foot pressure zone. Constructing this reservoir will
eleminate some of the water demand currently supplied by the 713-foot
pressure zone.
This project will include supply piping between the existing 10-million gallon
transfer pump station and the new reservoir. The reservoir will be completely
buried with a two and half acre park on top.
|
|
Project Status
|
- Reservoir construction is complete.
- Park construction including final landscaping scheduled to be complete Fall 2008.
- Paving along project frontage on Bull Mountain Road scheduled for September 2008.
|
|
Contacts
|
Contractor: |
Emery and Sons Construction, Inc.
Tim Janesofsky, Project Manager
503-769-7751
Tim@EmeryandSons.com
|
| City Contact: |
Rob Murchison, P.E.
Public Works Project Manager
503-718-2699
robm@tigard-or.gov
|
|